Sub Contract work from Garments to Garments

Work Station sub contract

Sub Contract work from Garments to Garments is the common process when capacity going idle. The sub contract is not allowed to in 100% RMG export oriented garments factory commonly. But internally involving buyer and BGME both are concerning to execute the sub contract process by inter bond.

Sub contract is most essential job to take proper order form other factory. when capacity blank factory propose or hire some order to other factory, they factory dose offer minimum or low price. On the other hand, when capacity is full and give some order from other factory price will be high.

So, the management is concern about giving or take the sub contract order depended on capacity. The major part of sub contract order give or take by SMV of this order.

Style- 26321S002
Productivity Information:
Man70
Pdn/Hr166
SM13.90
Price Quotation: 
A. Considering  10% Profit
Factory Overhead             55.24
Nett Profit               6.14
Sales Price            61.38
CM Revenue             61.38
B. Considering  5% Profit
Factory Overhead             55.24
Nett Profit               2.91
Sales Price            58.15
CM Revenue             58.15
C. Considering  0% Profit
Factory Overhead             55.24
Nett Profit                  –  
Sales Price            55.24
CM Revenue             55.24
Sub Contract Pricing in different percentage

The sub contract pricing in different percentage when giving order from other garments factories the above calculation is most appropriate. You may details is below video.

Sub Contract Rate Offer

Please click for soft excel file>>>>